CleanSpark Releases August 2026 Operational Update

Construction ongoing for the Sandersville campus with $6.6 billion in contracted revenue

Receives notice of conditional batch zero classification by ERCOT for both sites in Texas

 CleanSpark, Inc. a market-leading data center developer released its unaudited Bitcoin mining and operations update for the month ended August 31, 2026.

“We continue making strong construction progress at our Sandersville site as we execute for our high-investment grade tenant,” said CEO and Chairman Matt Schultz. “In Texas, we support and remain fully committed to satisfying Governor Abbott’s audit directive with both ERCOT and the PUCT.  As part of that process, we have received notice of conditional classification by ERCOT for 585 MW of contracted capacity to receive batch zero baseload designation and 300 MW to receive batch zero studied load designation, as expected. We look forward to working collaboratively with all stakeholders to serve the needs of Texans while also delivering for our shareholders and customers.”

August 2026 Bitcoin Mining Highlights (Unaudited)

Production Metrics

Bitcoin produced

593

Peak single day bitcoin production

20.40

Average daily bitcoin production

19.12

CY2026 bitcoin produced

4,903

 

Fleet Metrics

Operational Hashrate1

 50 EH/s

Average operating hashrate

38.3 EH/s

Peak efficiency of deployed fleet

 16.07 J/Th

Deployed fleet as of August 31

201,269

 

Power Portfolio Metrics

GW under contract2

1.8 GW

Utilized MW3

808 MW

 

Bitcoin Treasury Activity

Total bitcoin holdings as of July 31

13,931

Bitcoin produced

593

Bitcoin sold at spot

(77)

Bitcoin sold pursuant to call exercises

(500)

Bitcoin sold related to delta neutral basis trade

(244)

Total bitcoin holdings as of August 314

13,703

Average price per bitcoin sold5

$65,420